Инструкция на Системы очистки коммунальных стоков Lowara серии DEPURBOX DUO
Системы очистки коммунальных стоков Lowara серии DEPURBOX DUO (с численностью до 20 человек). Инструкция по монтажу и эксплуатации.
Загружаем документ…
Текст инструкции
-
Lowara
it en STAZIONI DI DEPURAZIONE BIOLOGICA SERIE DEPURBOX BASE - MAXI - DUO BIOLOGICAL TREATMENT STATIONS DEPURBOX BASE - MAXI - DUO Istruzioni d’installazione e uso Installation and operating instructions it Conservate con cura il manuale per future consultazioni en Keep this manual for future…
-
Italiano
1. Generalità Col presente manuale intendiamo fornire le informazioni indispensabili per l’installazione, l’uso e la manutenzione delle stazioni di depurazione biologica a fanghi attivi serie Depurbox BASE, MAXI, DUO. Quanto contenuto nel presente manuale si riferisce al prodotto di serie come…
-
3.1.3 Luogo d’installazione
Non installate la stazione di trattamento dentro degli edifici. ATTENZIONE Installate la stazione all’esterno degli edifici in posizione interrata oppure sopra al suolo. Se installata fuori terra, si consiglia di prevedere una tettoia di protezione contro le intemperie (pioggia, vento,….) ed un…
-
Non scaricate il refluo trattato sul suolo (articolo 29 del D.Lgs. n.152) poiché non rispetta i limiti della Tabella n.4 , Allegato 5, del Decreto Legislativo 11 maggio 1999, n.152 successivamente aggiornato con il Decreto Legislativo 18 agosto 2000, n.258, a meno che non abbiate installato…
-
3 Preparate uno scavo avente le dimensioni come riportate in uno dei disegni della sezione 10.4., a seconda del tipologia e composizione della stazione di trattamento da installare. Realizzate un letto di appoggio in sabbia o pozzolana livellata e compattata (20-30 cm). Prendete bene le misure e…
-
7 Riempite d’acqua il sedimentatore primario e gli ossidatori sino a metà per stabilizzarne la posizione. Riempite lo scavo con strati di 30 cm di sabbia o pozzolana, bagnando moderatamente gli strati e compattando accuratamente il rinfianco. 8 Installate i pozzetti di ispezione in corrispondenza…
-
Funzionamento La stazione di trattamento serie Depurbox è un impianto di depurazione ad ossidazione totale con fanghi attivi che diviene completamente attiva dopo circa trenta giorni dal primo avviamento. In condizioni climatiche particolari (es. freddo intenso) potrebbe essere richiesto un tempo…
-
Assistenza Per qualsiasi richiesta fate riferimento al nostro Servizio di Vendita ed Assistenza. 7.5 Ricambi ATTENZIONE Precisate sempre l’esatto tipo di prodotto e il codice se dovete chiedere informazioni tecniche o particolari di ricambio al nostro Servizio di Vendita ed Assistenza. Usate solo…
-
Tabelle e disegni 10.1 Composizione 10.1.1 Depurbox BASE – Schema Coperchio (vetroresina) Tubo di ingresso DN 100 (PVC) Condotto di reflusso Eiettore venturimetrico (ghisa) Serbatoio (vetroresina) Pompa Lowara serie DOMO 7VX Tubo di mandata Tubo di uscita DN 100 (PVC) Tubo aspirazione aria (3/4")…
-
Targhe dati 10.2.1 Depurbox BASE Cod.: 109410500 XXXXXX 1 yyyymmdd 2 Codice: 109410500 XXXXXX 4 yyyymm 3 DP B OX_M 0012_A _SC Tipo Codice Data di produzione Numero di serie 10.2.2 Depurbox MAXI Cod.: 109410520 XXXXXX yyymmdd Codice: 109410520 XXXXXX Codice: 109410520 yyyymm XXXXXX yyyymm DP B OX_M…
-
Posizionamento e collegamenti idraulici 10.5.1 Depurbox BASE DP B OX_M 0022_A _SC Entrata femmina DN 100 (PVC serie pesante) Uscita maschio DN 100 (PVC serie pesante) Pozzetto di ispezione/prelievo campioni (a cura dell'installatore) Tratto di collegamento DN 100 (PVC serie pesante, a cura…
-
Variante per Depurbox DUO min. 0,40 m 4 DP B OX_M 0024_A _SC Entrata femmina DN 100 (PVC serie pesante) Uscita maschio DN 100 (PVC serie pesante) Tratto di collegamento DN 100 (PVC serie pesante, a cura dell’installatore) Raccorderia varia DN 100 (PVC serie pesante, a cura dell’installatore) Adesivo…
-
Depurbox MAXI e DUO (esempio) DP B OX_M 0025_A _SC 10.7 Variante fuori terra Depurbox Stazione di sollevamento Lowara tipo Singlebox 2 DP B OX_M 0026_A _SC 10.8 Variazioni tarature dopo trenta giorni dal primo avviamento 10.8.1 Valvola di regolazione aspirazione aria 1 2 ½ ~ 30° DP B OX_M 0009_A _SC…
-
Valvola di ricircolo fanghi (solo per Depurbox BASE) 2 1 ~ 45° ¼ DP B OX_M 0015_A _SC 1 2 Posizione della valvola nella fase di primo avviamento (della durata di circa trenta giorni) Posizione della valvola dopo la fase di primo avviamento 10.8.3 Programmatore orario a ciclo giornaliero Taratura di…
-
Depurbox Maxi e Duo (vasca Imhoff) – Pulizia dai fanghi 1 10.9.3 Depurbox Maxi e Duo – Pulizia dai fanghi 1 2 1/3 10.10 Accessori non compresi nella fornitura 10.10.1 Dimensioni consigliate per pozzetti di ispezione o di prelievo campioni 3 0,00 DN 100 50 DN 100 Ø 400÷500 400÷500 Ø 400÷500 1…
-
Sgrassatore (degrassatore) statico DGS - Composizione 1 5 DGS 50 Codice: 109410YYY XXXXXX yyyymm DPBOX_M0017_B_SC Coperchio (vetroresina) Tubo di ingresso DN 125 (DGS 50 e 100), DN 160 (DGS 150) Serbatoio (vetroresina) Tubo di uscita DN 100 Zona di raccolta grassi 10.10.2.1 Posizionamento…
-
Per fosse di diametro uguale o superiore a 160 cm si consiglia di realizzare una soletta in cemento dello spessore di circa 5 cm con rete elettrosaldata e installare un chiusino in corrispondenza del coperchio di ispezione. 10.10.2.2 Schema di installazione se il Depurbox è collegato sia alla cucina…
-
Aprite completamente il degrassatore. La presenza di una crosta biancastra galleggiante, creata dai detergenti, impedisce il deflusso dei materiali grossolani dalle tubazioni. Se lo strato galleggiante è di colore bruno-nerastro, la sua origine dipende da un eccesso di grassi solidificati. Smuovete…
-
Sabbia o pozzolana Pozzetto di ispezione con chiusino in ghisa Pozzetto di ispezione (a cura dell'installatore) Vasca Imhoff (presente nei modelli Depurbox MAXI e DUO) Depurbox Filtro DBF Pozzetto di prelievo campioni (a cura dell'installatore) Per l’installazione interrate procedete nel seguente…
-
Pozzetto di ispezione (a cura dell'installatore) Vasca Imhoff (presente nei modelli Depurbox MAXI e DUO) Depurbox Filtro DBF Pozzetto di prelievo campioni (a cura dell'installatore) 10.11. Esempi di installazione alternativa Ove lo spazio non consente uno sviluppo rettilineo dell’impianto di…
-
Parametri operativi
Tipo di insediamento Numero di abitanti equivalenti Volume utile totale Volume elementi plastici (denitrificazione) Volume filtro Volume di decantazione (chiarificazione) Abbinabile al Depurbox fino a litri litri litri litri Modello DBF10 DBF10 Residenziale 10 20 1150 1380 BASE e MAXI DUO…
-
Dotazione idrica unitaria allo scarico
(litri abitante giorno) Fattore di ossigeno fornito (kgO2/kgBOD5) Numero di abitanti equivalenti Portata massima oraria (l/h) Portata media oraria (l/h) Rendimento di depurazione (%) SS (mg/l) Tempo di sedimentazione primaria (ore) Tempo di sedimentazione secondaria (ore) Velocità ascensionale di…
-
English
1. en Overview The purpose of this manual is to provide the necessary information for proper installation, operation and maintenance of the Depurbox BASE, MAXI, DUO series of biological activated sludge treatment stations. The contents of this manual concern the standard product, as described in the…
-
3.1.3 Installation site
WARNING Do not install the treatment station inside buildings. Install the station outdoors, either in-ground or lying on the ground. If installed on the ground, erect a shelter to protect the product from the weather (rain, wind,….) and a lifting pit with booster pump (For further information →…
-
For the Italian market
Do not discharge treated wastewater into the ground (article 29 of Legislative Decree n° 152) as it does not respect the limits indicated in Table 4 , Annex 5, of Legislative Decree n° 152 of 11th May 1999, as amended by Legislative Decree n° 258 of 18th August 2000, unless an additional treatment…
-
Dig a hole of the dimensions indicated in one of the drawings of section 10.4., depending on the type and composition of the treatment station to be installed. Prepare a level compacted bed in sand or pozzolana (20-30 cm). Make sure the measurements are correct and adjust the thickness of the sand…
-
10 Complete filling. Tighten the air adjustment ball valves and filters by hand (→ section 10.1.1. part nos. 11 and 12). Make sure fresh air can enter the inlet pipes. Suitable systems should be used to signal the presence of the inspection pit covers in order to prevent any accidental damage. Leave…
-
Operation The Depurbox treatment station is an activated sludge total oxidation treatment system which becomes fully operative approximately thirty days after initial start-up. In particular weather conditions (e.g.: intense cold) more time may be required for the bacterial flora to form. The…
-
Assistance For any requirements, please contact our Sales and Service Department. 7.5 Spare parts WARNING Always specify the exact type of product and code when requesting our Sales and Assistance Service for technical information or spare parts. Only use spare parts to replace any components. The…
-
Tables and Drawings 10.1 Composition 10.1.1 Depurbox BASE – Diagram Cover (glass-reinforced plastic) Inlet pipe DN 100 (PVC) Backflow pipe Venturi ejector (cast-iron) Tank (glass-reinforced plastic) Lowara DOMO 7VX series pump Delivery pipe Outlet pipe DN 100 (PVC) Air inlet pipe (3/4") Air inlet…
-
Rating plate 10.2.1 Depurbox BASE Cod.: 109410500 XXXXXX 1 yyyymmdd 2 Codice: 109410500 XXXXXX 4 yyyymm 3 DP B OX_M 0012_A _SC Type Code Date of production Serial number 10.2.2 Depurbox MAXI Cod.: 109410520 XXXXXX yyymmdd Codice: 109410520 XXXXXX Codice: 109410520 yyyymm XXXXXX yyyymm DP B OX_M…
-
Installation diagrams and limits to supply 10.3.1 Do not drive over and/or walk on the covers DP B OX_M 0021_A _SC 10.3.2 Depurbox BASE DP B OX_M 0010_A _SC Inspection pit (provided by installer) Depurbox Sampling pit (provided by installer) Limit to supply 10.3.3 Depurbox MAXI and DUO DP B OX_M…
-
Positioning and hydraulic connections 10.5.1 Depurbox BASE DP B OX_M 0022_A _SC Female inlet DN 100 (PVC heavy series) Male outlet DN 100 (PVC heavy series) Inspection/Sampling pit (provided by installer) Connection piping DN 100 (PVC heavy series, provided by installer) Adhesive for PVC pipes…
-
Variant for Depurbox DUO min. 0,40 m 4 DP B OX_M 0024_A _SC Female inlet DN 100 (PVC heavy series) Male outlet DN 100 (PVC heavy series) Connection piping DN 100 (PVC heavy series, provided by installer) Sundry connectors DN 100 (PVC heavy series, provided by installer) Adhesive for PVC pipes…
-
Depurbox MAXI and DUO (example) DP B OX_M 0025_A _SC 10.7 Surface installation Depurbox Lowara Singlebox lifting station 2 DP B OX_M 0026_A _SC 10.8 Calibration changes thirty days after initial start-up 10.8.1 Air inlet adjustment valve 2 1 ½ ~ 30° DP B OX_M 0009_A _SC Position of valve during…
-
Sludge recirculation valve (only for Depurbox BASE) 2 1 ~ 45° ¼ DP B OX_M 0015_A _SC 1 2 Position of valve during initial start-up (lasting approximately thirty days) Position of valve after initial start-up 10.8.3 24H programmable timer S A S A Calibration set to ten minutes every hour during…
-
Depurbox Maxi and Duo (Imhoff tank) – Sludge removal 1 10.9.3 Depurbox Maxi and Duo – Sludge removal 1 2 10.10 Accessories not included in the supply 10.10.1 Recommended sizes for inspection or sampling pits 1/3 3 0,00 DN 100 50 DN 100 Ø 400÷500 400÷500 Ø 400÷500 1 DPBOX_M0016_B_SC 1 42…
-
DGS static degreaser - Layout 1 5 DGS 50 Codice: 109410YYY XXXXXX yyyymm DPBOX_M0017_B_SC Cover (glass-reinforced plastic) Inlet pipe DN 125 (DGS 50 and 100), DN 160 (DGS 150) Tank (glass-reinforced plastic) Outlet pipe DN 100 Fat collection area 10.10.2.1 Positioning, hydraulic connections…
-
For pits with diameters or 160 cm or more, make an approx. 5 cm thick concrete floor with electrowelded mesh and fit a manhole over the inspection cover. 10.10.2.2 Installation diagram if the Depurbox is connected to both the kitchen and the bathroom Inspection pit (provided by installer) DGS…
-
Fully open the degreaser. The presence of a floating white crust created by detergents prevents the large solids from flowing along the pipes. If the floating layer is brownish-blackish, it is caused by an excess of solidified fat. Detach and break up the floating layer with a rod. Break up this…
-
Sand or pozzolana Inspection pit with cast-iron manhole cover Inspection pit (provided by installer) Imhoff tank (for Depurbox MAXI and DUO) Depurbox DBF filter Sampling pit (provided by installer) For in-ground installation, proceed as follows: 1 Dig a hole of a suitable size (similar to the hole…
-
Inspection pit (provided by installer) Imhoff tank (for Depurbox MAXI and DUO) Depurbox DBF filter Sampling pit (provided by installer) 10.11. Examples of alternative installations If there is insufficient space for the treatment station to be installed in a straight line, different layouts can be…
-
Operating parameters
Type of premises Number of equivalent inhabitants Total useful volume Volume of plastic elements (denitrification) Volume of filter Settling volume Combinations with Depurbox up to litres litres litres litres Model DBF10 DBF10 Residential 10 20 1150 1380 BASE and MAXI DUO DPBOX_M0033_OT 10.12.3…
-
Per capita water supply to discharge
(litres/head/day) Supplied oxygen factor (kgO2/kgBOD5) Number of equivalent inhabitants Maximum flow per hour (l/h) Average flow per hour (l/h) Treatment efficiency (%) SS (mg/l) Primary settlement time (hours) Secondary settlement time (hours) Settlement rising speed (m/h) Sludge digestion volume…
Схемы, таблицы и рисунки — в просмотре документа выше. Клик по номеру страницы открывает её в просмотре.