1. INTRODUCTION
This Installation Manual is intended for professionals, qualified to install RHP Pro2 air handling units. Qualified professionals are people with sufficient professional experience and knowledge of ventilation systems and installation thereof, knowledge of electrical safety requirements and having…
-
RHP Pro2 units come in several sizes. Each size is designed for a specific air volume range
Unit size Maximum air volume, m3/h 12 2650 22 3900 32 5150 42 6800 52 9250 62 11300 72 15700 82 27500 92 33500 102 38000 112 46000 Maximum air volume may be limited according to the order, for example, if lower power fans are used or higher air volume is not required by the project requirements. For…
-
1.3.2. Heat pump section
Air-handling units are equipped with an integrated heat pump operating both in heating and cooling modes. All heat pump components and a rotary heat exchanger are installed in a heat pump section. This section is also fitted with a heat pump control electronics and automation box to which many of…
-
Rotor wheel of a rotary recuperator is belt driven by an electric gear motor. Brush seals are installed at the perimeter of a rotating wheel and between air flows to prevent different air flows from mixing. Recuperator section is also fitted with an automation box to which many of the main…
-
A heat pump assembly consists of a piping system containing refrigerant, compressor, two radiators (condenser and evaporator) and separate control electronics. If air velocity in the air handling unit is high (> 2 m/s), optional drop eliminators are installed by the condenser and/or evaporator…
-
Depending on the size of the unit, the heat pump unit may contain up to 3 independent circuits, each consisting of the same components (compressor, pipeline, valves and sensors). In such units, refrigerant coils (condenser and evaporator) of a heat pump also consist of several tiers, which are…
-
Air handling unit model / Vėdinimo įrenginio modelis
RHP PRO 32 Heat pump model / Šilumos siurblio modelis Maximum operating pressure Maksimalus darbinis slėgis P max [bar] Refrigerant / Šaltnešis 42 R454C Number of separate circuits / Atskirų kontūrų skaičius 1 Quantity of refrigerant / Šaltnešio kiekis 5,6 mR410A [kg] Hermeticaly sealed system /…
-
1.3.3. Recirculation Section
Recirculation section is intended for mixing extract and supply air for heating or cooling thereof by reducing energy consumption of heaters/coolers. 1. 1 2 3. 2. Fig. 6. Recirculation section 1 – air mixing damper, 2 – damper actuator, 3 – recirculation section label 1.3.4. Cooler and Heater…
-
Depending on the order, electric or water heaters may be selected. An electric heater section is fitted with heater control electronics and the main circuit breaker (see Chapter “Requirements for Electrical Connection”). A water heater is fitted with a return water temperature sensor, which protects…
-
1.3.6. Silencers
Noise suppressor sections are intended for reducing noise generated by an air handling unit and air flows. Depending on the unit type and location of a silencer section, suppressor sections may be separate for each air flow (e.g., for supply air only) or double, intended for both air flows. Silencer…
-
1.3.8. Smoke extraction section
The smoke extraction section is used to direct the gases and smoke generated by fire in the building, directly to the exhaust air fan, which throws them out, bypassing the AHU filters and the heat exchanger. Smoke ducts of the building are connected to a smoke bypass damper, which is mounted at the…
-
1.4. Inspection Sides
Depending on the installation position and connection of air ducts, RHP Pro2 air handling units are available in four inspection sides. Inspection side is determined by a supply air duct (SUP) position: L1 Air duct for supply air connected on the left bottom side of the unit EHA ETA ODA SUP L2 Air…
-
2. UNIT TRANSPORTATION AND STORAGE
Units must be transported and stored in their original packaging. During transportation, units must be properly fixed and additionally protected against possible mechanical damage, rain or snow. Only an employee qualified to operate a forklift truck or crane and familiar with the principles of cargo…
-
If fully assembled AHU will be lifted, not each section separately, it must be done using additional reinforced mounting frame. When the unit is ordered fully assembled, it will already be mounted on a reinforced installation frame at the factory. If the unit’s sections are transported separately…
-
B
L ≤ 2,5 m L 40 125 125-150* C 150 150 L/5 L/5 2,5 m < L ≤ 4 m 125 125-150* 40 (L-300)/2 (L-300)/2 150 150 L/5 L/5 C A 4 m < L ≤ 6,5 m 125 125-150* 40 (L-300)/3 125-150* A (L-300)/3 (L-300)/3 150 L/5 150 L/5 125 B 42 - 92 20 * In units of sizes 12-72 the frame height is 150 mm; in units of sizes…
-
3. MECHANICAL INSTALLATION
3.1. Requirements for Mounting Location and Installation Base RHP Pro2 air handling units are designed for ventilation of medium or large commercial or industrial premises (e.g., stores, offices, hotels, etc.) where standard air temperature and humidity is maintained. These units are not intended…
-
3.2. Inspection Area
Based on its type, an air handling unit may be installed indoors or outdoors. When selecting an installation or mounting location, you must foresee sufficient and security compliant access space for repair and maintenance operations. The unit must be installed in a way to allow partial or full…
-
3.3. Door Handles and Hinges
RHP Pro2 door handles are designed in such a way that the unit door does not swing open due to the pressure accumulated inside the unit and does not injure the person opening the door. By pressing the handle, the door slightly opens and locks to release air pressure inside the unit. Return the…
-
Fig. 21. External connection and sealing of sections 1 – installation frame, 2 – nut M10, 3 – washer, 4 – screw M10, 5 – adhesive gasket, 6 – gasket on a shelf between different air flows, 7 – external tightening elements Depending on the unit size and purpose of sections thereof, separate sections…
-
Fig. 22. Types of internal section connections 1 – threaded bushing, 2 – spacer 35 mm, 3 – washer, 4 – screw M6, 5 – spacer 70 mm, 6 – grommet d29, 7 – adhesive gasket Sections are tightened at the inside corners as well as in the middle at the shelf separating different air flows. For easier access…
-
3.5. Installation of External Heating/Cooling Devices
Based on their equipment, RHP Pro2 air handling units may be operated with various heating or cooling devices. Heaters/coolers are usually installed in separate sections that are connected at the end of the unit (in the supply air stream). For air handling units with R1 or L1 inspection sides…
-
Pipes of water heater and cooler are connected to a water mixing unit (PPU) that supplies hot/cold water from the building’s water system. Heat exchangers for direct evaporation (DX) coolers/heaters are factory-filled with nitrogen gas. Before connecting a heat exchanger to a refrigerant system…
-
3.6. Connection of a Condensate Drain
p<0 Ø40 mm Ø40 mm During operation of the heat pump, air humidity condensates and accumulates in specially designed condensate trays. Condensate is removed from condensate trays via drainage pipes, therefore a condensate drainage system must be connected. Drainage piping must be at least 40 mm in…
-
3.7. Connection to Air Ducts
• • • • Ducts connecting the unit to the exterior of the building must be insulated (insulation thickness 50–100 mm) to prevent condensation on cold surfaces. Air intake and exhaust ducts must be fitted with air shut-off dampers (electric with actuators) to protect the unit from exposure to climatic…
-
AHU size (HP size)
Qmin, m3/h 12 (11/11) 594 12 (16/15) 655 22 (18/17) 819 22 (20/19) 901 32 (25/23) 1352 32 (38/34) 1597 42 (28/26) 1761 42 (41/40) 1863 52 (29/27) 2068 52 (45/45) 2068 62(47/47) 1945 62 (59/58) 2048 72 (49/49) 2007 72 (83/84) 2007 82 (52/52) 2089 82 (89/90) 1986 92 (54/54) 2212 92 (104/102) 2150 102…
-
RHP PRO2 12-72
-
RHP PRO2 82-92
a+100 b/2 b/2 c+100 a b>1110 c a+100 b c+100 a b<1110 c Fig. 34. Installation of a separately ordered protective roof Part count and measurements may differ depending on the unit type or project requirements. UAB KOMFOVENT we reserve the right to make changes without prior notice RHP…
-
4. ELECTRICAL INSTALLATION
Only qualified professionals may perform electrical installation works in accordance with the manufacturer’s instructions and applicable legal acts and safety requirements. Before installation of any electrical components: • • • • Make sure the unit is unplugged from the mains. If the unit has been…
-
If circuit breaker bracket is used, it must be mounted on the edge of the unit casing, otherwise self-tapping screws may damage wires or tubing that is routed inside. Units fitted with an additional electric heater section will be equipped with a separate main circuit breaker inside the section. OFF…
-
4.2. Connection of Electrical Components
All internal and external devices are connected to the main board of the C5 control panel (RG1 in wiring diagrams) located in the automation box. Automation box is fitted at the front of the unit, top part of the heat exchanger section. Box is airtight and is opened by removing four screws and…
-
Terminals for the external elements of the controller board are numbered and are used only to connect external components. These may remain empty if no additional features are required. B9 Exhaust air pressure sensor Humidifier control Cold water mixing valve / DX capacity control Hot water mixing…
-
Fig. 41. Return water temperature sensor with thread1
B1 (11–12) – terminal for a supply air temperature sensor (NTC 10kΩ) for controlling air temperature. Fig. 42. Supply air temperature sensor For the most accurate temperature measurement, sensor in a duct must be installed after all heating/cooling devices at least two duct diameters away from the…
-
Indication (40–42) – terminals are used when a normally open (NO) contact is necessary for operation status or fault indication. Terminals 40 and 42 are closed when AHU is in operation, thus it can be connected to any external device, which needs such a signal (for example humidifier). Terminals 41…
-
4.3. Control Panel Installation
The control panel must be installed in a room with: Ambient temperature – 0..40°C; Relative humidity – 20..80 %; Guaranteed protection against accidental water drops. Control panel can be mounted in a concealed mounting box or directly on the wall (screws supplied with the panel). You can also use…
-
4.4. Connection of Cables and Wires Between Sections
X1 X1 2 2 Before fastening parts of the air handling unit, you shall connect connecting cables and wires of the sections. Cable connectors are labelled with connector numbers; only connect connectors with the same number. Number of cables and connectors in different sections may differ depending on…
-
4.5. Connecting the Unit to the Internal Computer Network or the Internet
Your AHU may be controlled not only with a control panel, but also with a computer or smart phone. For this reason the unit must be connected to the internal computer network or the Internet. In case of a computer, the unit is controlled via a web browser, and in case of a smart phone - via the…
-
In order to control your AHU over the Internet, connect it to the network router which has access to the Internet. Follow the router manual to configure port forwarding to the unit IP address. Depending on whether you will use your computer or smart phone with the Komfovent app to control your AHU…
-
5. FILTERS
Air filters are intended for removing dust, bacteria and other fine particles from the supplied and extracted air. RHP Pro2 air handling units are fitted with bag filters, since they have a larger filtering surface than compact filters and will require less frequent filter replacement. Filters are…
-
6. COMMISSIONING AND INSPECTION OF THE UNIT
Before switching on the device, check for foreign objects, debris or tools inside the unit. Make sure that air filters are installed and condensate drainage is connected (if necessary), fill the siphon with water. Make sure that the ductwork is free from obstructions such as fully closed diffusers…
-
tap
If the unit is connected to the mains, the control panel will display a home screen or a screen saver that you can switch off with a single To start an air handling unit or change a ventilation mode: Change operation mode? During the first minute of starting the unit, the unit automation checks the…
-
To turn of the AHU and return to a home screen
6.2. Starting the Unit With a Computer If the unit was ordered without a control panel or it is not used, you can start it with your computer. In this case the unit is controlled via a web browser. Connect your computer directly to the AHU or to the same computer network as described in Chapter 4.5.…
-
To start the unit and change the ventilation mode settings
1. Press button “Modes”. 2. Select a desired ventilation mode from the list. 3. Enter desired air flow and temperature in the selected mode settings. 4. Press “Save” button at the bottom of the screen. You can stop the unit by pressing ON/OFF button in the “Overview” window. UAB KOMFOVENT we reserve…
-
6.3. Calibration of Clean Filters
RHP Pro2 control automation continuously monitors filter contamination. Pressure drop of clean filters is preset in the factory. If filters are from another manufacturer or of different filtering class, we recommend performing initial calibration of clean filters before commissioning of the unit.…
-
6.4. Quick Inspection
The first time you start your device, make sure that: Task Yes No Comments Control panel is working, responds to touch, no error messages All air filters are installed Air dampers fully open There are no unusual noise or vibrations Changing the ventilation modes changes the fan speed The unit is…
-
APENDIX NO.1
WARRANTY INFORMATION Dear Customer, KOMFOVENT thanks you for your choice. We are pleased that you have chosen us and will strive to ensure you are satisfied with your purchased product. To avoid misunderstandings, we kindly ask you to read the installation and operating instructions of the product…
-
WARRANTY CONDITIONS
1. The warranty does not apply in the following cases: 1.1. If the product usage or operating conditions, as specified in the installation and operating instructions, are violated; 1.2. If the storage conditions of the unit are violated; 1.3. If there are signs indicating attempts of unqualified…
-