Inverter Modular Heat Pump
Owner's Manual Inverter Modular Heat Pump Models: CH-HP 36UIMNM CH-HP 65UIMNM CH-HP 70UIMNM CH-HP 77UIMNM Thank you for choosing our product. For proper operation, please read and keep this manual carefully. If you have lost the Owner’s Manual, please contact the local agent or visit…
-
To Users
Thank you for selecting Cooper&Hunter’s product. Please read this instruction manual carefully before installing and using the product, so as to master and correctly use the product. In order to guide you to correctly install and use our product and achieve expected operating effect, we hereby…
-
1 Safety Notices
Warning:If not abide strictly, it may cause severe damage to the unit or the people. Note:If not abide strictly, it may cause slight or medium damage to the unit or the people. This sign indicates that the operation must be prohibited. Improper operation may cause severe damage or death to people.…
-
(1)Do not install the unit where there is high-intensity magnetic field or it is highly basic
or acid or the voltage is quietly unstable. (2)Do not install the unit where there would be leaked inflammable gas, as it would lead to fire hazards. (3)The outer casing of the unit should be grounded. Do not connect the grounding line to the gas line, water line, lightning rod or communication…
-
CAUTION
(1)Installation should be done in accordance with this manual. Please read it manually prior to startup or troubleshooting. (2)Installation should be done by qualified servicemen, as incorrect installation would lead to water leakage, electrocution or fire hazards etc. (3)Before installation, check…
-
(1)Do not let the unit out of the designed application range; otherwise it would cause
the heat exchanging tube cracking, refrigerant leakage or even explosion. (2)Do not let the cold/heat source directly act on the stored foods, plants, animals, precision instruments, and curiosities, otherwise their quality would be degraded. (3)Only circulating water with satisfactory water qualify…
-
CAUTION
(1)Do operate the unit in accordance with this manual and read it carefully before startup or troubleshooting. (2)Do turn on or off the unit with the controller. ◆Safety Precaution for Handling of the Unit Safety Precaution for Handling of the Unit WARNING (1)Please contact the contractor for…
-
Correct Disposure
This marking indicates that this product should not be disposed with other household wastes throughout the EU. To prevent possible harm to the environment or human health from uncontrolled waste disposal,recycle it responsibly to promote the sustainable reuse of material resources. To retuern your…
-
2 General Introduction
See the nameplate for the main technical data. The all-inverter modular air-cooled chillers are capable of performing cooling all year around with high energy efficient. It requires no cooling towers and is quite applicable to waterdeficient areas, and can be widely used at newly built or…
-
Two water pumps can work alternately with equilibrium runtime so as to extend their service
life and lower the maintenance difficulty. 2.2 Principle Diagrams 3 Operation Range Please run the unit under the specified operation range as shown in the table below: ■ R410A Series Water Side Item Air Side Leaving Water Water Temperature Ambient DB Temperature(℃) Difference(℃) Temperature(℃)…
-
4 Outline Dimensions
-
5 Installation Instructions 5.1 Pre-check Installation should be performed by the skilled technician to guarantee the normal operation and prevent malfunctions and please read this manual carefully prior to installation. The chiller is manufactured, inspected and tested strictly in accordance with…
-
When there is damager or any other question, contact the local sales representative for
applicable solutions. NOTE After the acceptance check, take necessary protection to the unpacked equipment. Note that it is not recommended to unpack the equipment too early to avoid any unexpected damage. 5.3 Handling and Lifting Each unit will undergo a series of strict factory inspections and…
-
5.4 Installation Foundation and Service Space
(1)Installation foundation shall be designed by the qualified designer in accordance with the actual condition. (2)A rubber pad shall be placed under the base of each single unit and then secured on the ground or the roof. Alternatively, each single unit can be placed side by side on the parallel…
-
Note: diagrams above are just for reference and not in real proportion
5.5 Vibration Reduction The unit shall be securely attached to the foundation through the mounting hole by following the steps below. 13
-
(1)Be sure the planeness of the concrete foundation is within ±3mm and the foundation
shall be covered by a rubber pad. (2)Lift the unit until to the height where it is available to install the spring shock absorber. (3)Remove screws fixing the spring shock absorber. (4)Place the unit on the spring shock absorber and align the bolt holes of the spring shock absorber with the mounting…
-
Never use salt mixture to prevent the unit from being corroded
■ How to install the water system ■ How to drain the water system: (1)Loosen screws around the panel and then take down it. 15
-
(2)Remove anticlockwise the blind plug located at the bottom of the heat exchanger to let
the chilled water flow out, after that, tighten the blind plug and reinstall the panel. (Note: place the drainage equipment beneath the drain pipe to prevent pollution caused by the drain water. NOTE Keep the purge valve of the water system open in order to drain the evaporator and condenser…
-
corresponding wiring board of any one unit, while those for the error indicator and extemal
passive contact switch should be wired to the corresponding wiring board of all units as shown in the figure below. 7.2 Specification of Power Cord and Air Switch See the table below for selectin of the power lines and the air switches. Model Power Supply CHHP36UIMNM 380V~415VAC 3Ph 50Hz CHHP…
-
CHHP70UIMNM
380V~415VAC 3Ph 50Hz CHHP77UIMNM 380V~415VAC 3Ph 50Hz Notes: (1)The specifications of the breaker and power cable listed in the table above are determined based on the maximum power (maximum amps) of the unit. (2)The specifications of the power cable listed in the table above are applied to the…
-
(4)Any damage caused by the improper external wiring shall be at the installer’s expense
WARNING Only copper conductor is allowed. ■ How to wire the power lines to the electric box (1)The power cord must be routed inside the conduit. (2)The power cord must enter the electric box through a rubber or plastic ring to avoid any damaged caused by the sharp edge of the metal sheet. (3)The…
-
be installed with a suitable cord anchorage against cord loosing.See the wiring
diagrams below for external wiring. CH-HP36UIMNM, CH-HP 65UIMNM, CH-HP70UIMNM, CH-HP77UIMNM (4)The unit shall be grounded reliably and never connect the ground wire with the gas fuel pipe, water pipe, lightening rod or telephone line. (5)After wiring, O-rings should be tightened to prevent coming of…
-
(2)The electric box will send the control signal (220 AC, 5A) to control the chilled water
pump and auxiliary electric heater, however, never do not drive them directly through the control signal but through their AC contactors. (3)Switching signals (220VAC, 2A) for the running and error indicators are available for the electric box. (4)The remote switch control signal is available for…
-
7.5 Networking and Wiring between Units
Notes (1)As shown in the diagram above, CN33 and CN25 of all modules are connected by a three-core four-pin shielded communication line whose ground wire will be linked to the terminal near the main board. 22
-
main board of any unit by a four-core four-pin shielded communication line whose ground wire will be linked to the terminal near the main board. (3)The power lines should be connected to L1, L2, L3, and N at XT1 through a piece of four-core rubber sleeve cable as shown in the figure above. (4)There…
-
Note: the black block represents where the projecting lever of the toggle switch is
7.7 Jumpers When it is required to replace the main board, be sure the main board can match with the applicable jumpers. Table 7.7.1 Jumpers List Model Jumper No Code Matched Compressor QXAS- CH-HP36UIMNM 4202021905 CH-HP65UIMNM 4202021907 QXASH80zN345H CH-HP70UIMNM 4202021906 QXASH80zN345H…
-
8 Commissioning and Maintenance
The unit shall be maintained periodically by the skilled servicemen from C&H or a designed person under our professional guide to guarantee the unit operates reliably in a long term. 8.1 Check before Startup Please finish the following steps before staring the system. (1)Before energization, be sure…
-
Fe
mg(Fe)/L Total hardn- S2- mg(S2-)/L ess NH4+ SiO2 <1.0 <0.3 Undetecta- Undet- ble ectable mg(NH4+)/L <1.0 <0.3 mg(SiO2)/L <30 <30 NOTE:“○”indicates possible corrosion or scaling. Even if the water qualify is under the strict control, calcium dioxide or other minerals will still form on the surface…
-
Precautions (1)Although the cleaning agent is innocuous,care also should be taken not to let it spill into eyes. (2)The serviceman with injuries on the hand is not allowed to take this task. Check the running status before and after cleaning, summarize the cleaning effect and record the running data…
-
will tell “As ambient temperature is low, startup is not allowed”. At this point, the auxiliary
electric heater will not work, with the running indicator lighting off and both the water pump and compressor stopped. NOTE When the unit is ready to perform heating but water temperature is below 20℃, in order to keep stable and reliable operation, please do not start the terminal units until water…
-
8.9 Refrigerant Charging
Refrigerant charging should be done based on the discharge and suction pressure. An air tight test must be taken on the condition refrigerant leaks or some part is required to be replaced. Refrigerant charging comes into two cases stated below. ◆ Complete charging In this case, take a leakage test…
-
(7)Clean up the pipeline
8.11 Freeze Protection When the flow passage of the shell-and-tube heat exchanger is frozen up, it would cause serious damage to the heat exchanger, such as cracking and leakage which are out of warranty, therefore, the user should take measures stated below for freeze protection: (1)In order to…
-
Weekly Maintenance (1)Check the main unit, like if the compressor runs with abnormal noise, if the distribution box is attached securely and if the pipeline generates abnormal vibration or leakage. (2)Record key parameters, like pressure, pressure etc. ■ Quarterly Maintenance (1)Check the electric…
-
9 Troubleshooting and After-sales Service
9.1 Troubleshooting Measures Possible Causes Troubleshooting Measures 1.Uncomplete vacuuming. 2.Too high envivornment 1.Revacuum the system and recharge refrigerant. temperature. 3.Condenser fins are dirty 2.Improve ventilation. 3.Clean condenser fins. Shutdown against high pressure protection of…
-
Failed startup of the
compressor 1.The overcurrent relay 1.Replace it. tripped off and the fuse was burnt out. 2.Check wiring of the control system. 2.The control circuit was open. 3.Check the power supply. 4.See corresponding 3.There is no current. statement above. 4.Low/high pressure protection. 5.Replace it. 6.Check…
-
1.The entering and leaving
Protection against the failed 4–way valve water temperature sensor fell off or installed incorreclty. 2.The 4–way valve was damaged. 1.Check if the entering and leaving water temperature sensors were installed correctly and if silica gel at the probe for heat conduction was applied properly.…
-
Appendix A: Inspection Records Prior to Commissioning
-
Appendix B: Trial Run and Commissioning Records