Service & maintenance
-
1.0 Installation
1.1 Product description Lindab has developed a supply air beam, Celo, which can be installed above a suspended ceiling. Thus, you can conceal the ventilation and cooling features and create an unbroken ceiling without visible technical installations. The Celo concept has been developed together with…
-
1.5.1 Push-on fittings
Please ensure that all pipes and fittings are undamaged, as even small dents and scratches potentially pose a risk of leakage in the system. Always remember to do a pressure test after assembly of the pipe work. Both flow and return pipe is covered by a plastic or rubber protection cover, which…
-
Push-on valve
Notice! The connection pipes are internally soft-welded why it’s not allowed to solder the beam to the pipes. 1.5.2 Compression fitting Please ensure that all pipes and fittings are undamaged, as even small dents and scratches potentially pose a risk of leakage in the system. Always remember to do a…
-
–– The copper insert should be placed inside the pipe on the beam. Always support
the copper pipe coil when inserting the copper insert into position. Mount a compression coupling and/or a valve to the pipe. Don’t stress the nut too much, since this may crush the pipe. Notice! The connection pipes are internally soft-welded why it’s not allowed to solder the beam to the pipes.…
-
After removing the protection cover, make sure that the pipe is intact and undamaged, especially at the pipe end. Crocked or in other ways imperfect pipe ends will result in leaks. Deburr the pipe on the inside and the outside, using a deburring tool before installation Mount a push-on fitting to…
-
2.0 Commissioning
2.1 Product labeling Fig.1: Label location exterior (Air connection end) On the label you’ll find: Order: Order identification number. Pos: Order position. Product: Product configuration. Project: Project name. Mark: Marking noted on order. Nozzles: Number of nozzles. Plugs: Number of plugged…
-
2.2.2 Calculating the airflow
After measuring the static nozzle pressure, calculate the air flow per nozzle: q=0.0209 ∙ √P q = air flow per nozzle P = static nozzle pressure After finding the air flow per nozzle, find the needed number of open nozzles: q tot/q=n open q tot = total air flow n open = open nozzles Alternatively…
-
3.0 Maintenance
The interval of cleaning depends on the indoor environment where the beam is placed. Under optimal conditions the Celo beams only need cleaning every 5 years. 3.1 Cleaning instructions Clean underneath the battery with a vacuum cleaner and a piece of wet cloth Only use lukewarm water and a mild…
-
4.0 Product and system specification
4.1 Material data Celo 4.2 Weight, kg/m 6.5 Water content, cooling, l/m 0.25 Copper pipes, quality SS/EN 12449 Pressure class PN10 Environmental declaration Please visit www.lindqst.com • Select Documentation Finder • Select “Celo” • Select “Environmental declaration” 4.3 Working and test pressure…
-
The water velocities should not exceed 1m/s, and should be kept as close to the nominal flow as possible to minimize noise and optimize the energy yield There should be used in-line strainers to remove dirt particles from the water. If the water contains any additive inhibitor this must be…
-