USER MANUAL AND INSTALLATION INSTRUCTIONS ТЕХНИЧЕСКОЕ РУКОВОДСТВО И ИНСТРУКЦИЯ ПО ЭКСПЛУАТАЦИИ
-
Congratulations on your choice
Поздравляем Вас с Вашим выбором Your boiler is electronically controlled and has electronic ignition. Ваш котел управляется электроникой и имеет электронный розжиг The materials it is made of and the control systems it is equipped with give you safety, a high level of comfort and energy savings to…
-
is fitted with all the safety and control devices required by the current Regulations; Ensure that the installer has connected the pressure relief valve outlet to a drain pipe. The manufacturers are not responsible for damage caused by opening of the pressure relief valve and consequent escape of…
-
Boiler installation and commissioning tips
¾ Keep the boiler clear of dust during installation and in particular do not allow any dust or debris to enter the top of the boiler where the flue connection is made. It is recommended that you put a dust sheet over the top of the boiler until you are ready to make the flue connection. ¾ The…
-
Some products incorporate an anti cycling time delay. It is normal when first switching the boiler on for the boiler to operate on heating for a few seconds then switch off. After 3-4 minutes has elapsed the boiler will then re ignite and operate perfectly normally. The ignition delay cycle does not…
-
1. Appliance description
1. Описание устройства 1.1. Overview 1.1. Вид Fig. 1.1 1. Case front panel 1 Передняя панель корпуса 2. Control panel 2 Панель управления 3. Control panel cover 3 Крышка панели управления 1.2. Control Panel 1.2. Панель управления 4. Pressure gauge 5. Function switch and c.h. temperature adjustment…
-
Fig. 1.2 1.4. Technical data 1.4. Технические характеристики For detailed technical data see section 4.4 of this manual. Для более детальной информации см. разделы 4.4 настоящего рук-ва Fig. 1.3 2
-
1.5. Operation lights
1.5. Индикаторы функций Three lights (7 in Fig. 1.3) give detailed indication regarding the operation of the boiler. The following table gives the relationship between each of the possible light combinations and their meaning. Три лампочки (7 на рис.1.3) дают подробную информацию о работе котла.…
-
2. Instruction for use
2. 2.1. Warnings 2.1. Предупреждения In order to guarantee safety and correct operation, it is essential that all the tests are carried out by a competent and responsible service engineer before lighting up the boiler. Чтобы гарантировать безопасную и правильную работу, перед его запуском…
-
Jnrhsnm Pfrhsnm Normal filling pressure = 1bar Yjhvfkmyjt Lfdktybt Open Close 4 Fig. 2.2 Fig. 2.1 If you experience any difficulty with the operation of the boiler, switch off the boiler immediately at the fused spur isolation switch and contact your Installer or an approved Service Engineer Always…
-
Turn on the electricity supply to the boiler, switching on the fused spur isolation switch. The appliance operation light 7 (Fig. 1.3) will flash every 4 seconds (stand-by condition). 2 Включите электропитание котла. Индикатор котла 7 (рис.1.3.) будет моргать каждые 4 секунды (состояние ожидания) 3…
-
Adjustment of the boiler temperature alters
the gas flow at the burner according to the thermal demand in the system. So it is usual to see the burner lit at the minimum level for more or less long periods. Регулировка температуры влияет на количество газа, подаваемого на горелку в соответствии с тепловыми потребностями системы. Поэтому, если…
-
Minimum
Maximum vbybvev vfrcbvev Fig. 2.8 Adjustment of the d.h.w. temperature is completely separate from that of the c.h. circuit. The adjustment system integrated within the boiler automatically controls the flow of gas to the burner in order to keep the temperature of d.h.w. delivered constant, between…
-
install a small water treatment device or softener. With such a device you should avoid periodic descaling. Consequently, the d.h.w. heat exchanger will keep its performance consistent for a longer period of time with resulting gas savings. If the demand for d.h.w. is so great as to prevent reaching…
-
3. Useful advice
3. 3.1. Central heating 3.1. Центральное отопление For reasonably economical service install a room thermostat. Never shut off the radiator in the area where the room thermostat is installed. Для более экономного использования установите комнатный термостат. Никогда не перекрывайте радиатор в том…
-
During the service, the most important
components of the boiler will be inspected and cleaned. This service can be part of a maintenance contract. В процессе обслуживания, будут осмотрены и очищены наиболее важные детали котла. Такой сервис должен быть предусмотрен в договоре не сервисное обслуживание. В особенности, мы рекомендуем…
-
For the first lighting up and following
maintenance procedures for the gas supply, it may be necessary to repeat the resetting operation several times so as to remove the air present in the pipework. If noises due to air bubbles are heard during operation... you should check that the pressure on the pressure gauge ( Fig. 2.2) is not below…
-
than those mentioned here, switch off the boiler, as described in section 2.6 and call a competent and responsible service engineer. 14 В случае возникновения этой или других проблем, не описанных в данном руководстве, отключите котел как это указано в разделе 2.6 и пригласите к специалистам…
-
4. Technical information
4. 4.1. Overview 4.1. Вид 15. Main circuit drain cock 31 16. C.h. pressure relief valve 17. Automatic valve air 32 purger 18. Pump vent plug 30 19. Pump 33 20. D.h.w. flow switch 29 21. Gas valve 22. D.h.w. probe NTC 23. Primary switch temperature circuit flow 24. C.h. temperature probe NTC 25.…
-
4.4. Technical Data mod.M97.23SM
4.4. Технические характеристики Nominal heat input Номининальная потребляемая мощность Minimum pressure Минимальное давление l/min л/мин 2,5 ΔT=25 / 25°K рост l/min л/мин 13,4 ΔT=35 / 35°K рост l/min л/мин 9,5 Nom Норма Min Мин Max Макс 2000 1700 2500 20 17* 25 2900 2000 3500 mbar мбар Pa Па 3700…
-
Injectors Сопла
Natural G20 Природный газ G20 Butane G30 Бутан G30 Propane G31 Пропан G31 N° φ mm Gas rate Расход газа Gas Газ Natural G20 Природный газ G20 Butane G30 Бутан G30 Propane G31 ПропанG31 Min Мин Max Макс 1,16 2,71 0,87 2,02 0,85 1,99 3 m /h 3 м /час kg/h кг/час kg/h кг/час Electrical data Электрические…
-
4.5. Hydraulic specifications
4.5. Гидравлические характеристики Fig. 4.4 The hydraulic specifications in Fig. 4.4 represent the pressure (available head for the central heating system) as a function of the flow rate. The load loss due to the boiler has already been subtracted. Output with thermostat cocks shut off…
-
Capacity
l Объем л Pre-load pressure Предварительное давление Maximum volume water in the system Максимальный воды в системе of объем 6,0 KPa/кПа 100 bar/бар 1,0 l л 132 Tab. 4.1 * Where conditions are: Average maximum temperature of the system is 80°C Initial temperature when filling up the system is 10°C…
-
5. Installation
5. 5.1. Warnings 5.1. Предупреждения The use of gas appliances is subject to statutory control; it is essential to observe the current regulations and laws in force. Использование газовых приборов подлежит контролю; следует выполнять установку в соответствии с действующими нормами и…
-
- The boiler must be fixed to a strong wall. The dimensions for the exhaust fume duct detailed in section 5.7 and the correct procedures for installing the duct, depicted in the instruction leaflet included with the flue kit, must be complied with during installation. To allow maintenance procedures…
-
Utilise the paper template supplied with the
boiler to determine the fixing position for the bracket and boiler. Securely mount the bracket to the wall using appropriate fixings suitable for the type of wall construction and capable of supporting the total (wet) load. Refer to the weight given in the technical data tables specific for each…
-
5.5. Joints
5.5. Подсоединения If the C.h circuit is above the boiler level, it is advisable to fix the C.h. cocks to isolate the circuit and facilitate the maintenance. Если контур отопления находится выше уровня котла, рекомендуется установить запорные краны на подачу и обратку, чтобы упростить обслуживание…
-
5.7. Fitting the flue system
5.7. Подсоединение системы отвода отходящих газов (дымохода) Refer to the assembly instructions contained within the chosen flue kit packaging for the correct assembly and installation. Для правильной установки соблюдайте инструкции, содержащиеся в выбраном Вами комплекте отвода отходящих газов.…
-
5.9. Choice of Flue
5.9. Выбор дымохода The following flue kits are available for connecting to the boiler: Котел может быть подключен к следующим стандартным системам отвода отходящих газов: Стандартный горизонтальный набор для дымохода (рис.5.6А) Коаксиальный 60/100 мм - номинальная длина 1 м Этот набор обычно…
-
B
φ 60/100 L max = 4 m L min = 0,3 m Длина макс.=4м Длина мин. = 0,3м L A L φ 60/100 C 90° = - 1m 45° = - 0,5m Fig. 5.6 AIR Restrictor ограничитель воздуха Gasket 90° = -1,65m 45° = -0,9m Fig. 5.7 Twin pipe kits ø 80 mm ( Fig. 5.7) Various twin (split) pipes kits and optional accessories (elbows) are…
-
When fitting the 80/80 flue kits where the
equivalent flue length exceeds 7 m a condensate collector and syphon are required. The syphon must also be connected to a suitable drain. The graph in Fig. 5.9 and the following table demonstrate the allowable lengths for the flue exhaust pipes and the air supply with the 50 mm air restrictor (Fig.…
-
90° = -1m
Max length =8,5m Vfrc Lkbyf =8,5 v 45° = -0,5m Fig. 5.10 Vertical flue kit – condensation When fitting the 80/125 flue kits where the equivalent flue length exceeds 1 m a condensate collector and syphon are required. The syphon must also be connected to a suitable drain. Diameter size (mm) Max…
-
H
I H I Fig. 5.12 Fig. 5.11 4 Loosen the screws J and remove the service panel (Fig. 5.13). For the electrical connection to the boiler use electric wires which conform to the current regulations, with flexible cord, each core having a cross section area not less than 0,75 mm2. 4 Ослабьте винты J и…
-
To the fused
spur isolation switch L N К автомату K 3 2 Power supply terminal block Блок питания 1 External controls terminal block Блок внешнего контроля Fig. 5.14 6 Do not connect live wires to terminals to which the room thermostat must be connected. Connect the earth wire (yellow/green). The earth wire must…
-
Клапан с
электроприводом Комнатный термостат Room thermostat Motor operated valve Power supply terminal block L N T Комнатный термостат Room thermostat V Блок питания T N L External controls terminal block 3 Блок внешнего контроля External controls terminal block 1 Блок внешнего контроля Fig. 5.15 Fig. 5.16…
-
6. Commissioning
6. Ввод в эксплуатацию 6.1. Electrical installation 6.1. Монтаж электрической части Preliminary electrical system checks to ensure electrical safety shall be carried out by a competent person. i.e. polarity, earth continuity, resistance to earth and short circuit. If a fault has occurred on the…
-
6.4. Initial filling of the system
6.4. Первичное системы заполнение 1 Open the c.h. flow and return cocks. 1 2 Remove the front panel of the case (see the section 8.2 in this manual. 2 3 Unscrew the cap on the automatic air purger valve 17 (Fig. 6.2) one full turn and leave open permanently. 3 4 Gradually open stopcock at the…
-
If external controls are fitted (e. g. Timeclock,
room thermostat) ensure they "call for heat". 1 Turn on the electricity supply to the boiler, switching on the fused spur isolation switch. The appliance operation light 7 will flash every 4 seconds. 2 Turn the function selector 5 as in Fig. 6.3. The appliance operation light 7 will flash every 2…
-
Loosen the internal screw 35(Fig. 6.7) on the Outlet Pressure Test Point of the Gas Valve and connect a pressure gauge using a suitable hose. 5 To adjust the minimum pressure, enter a programming mode following the instructions below. 4 Ослабьте внутренние болты 35 (рис.6.7) на выходной контрольной…
-
Setting values
Значения настройки Fig. 6.6 = Lamp ON = Индикатор горит 11 11 Compare the value on the gauge with the values on the following table (Tab. 6.1). To adjust the minimum pressure rotate the minimum adjustment A (Fig. 6.7) Сравнить показания манометра со значениями в таблице (Таблица 6.1). Для…
-
If external controls are fitted (e. g. Timeclock,
room thermostat) ensure they "call for heat". Отрегулировать максимальное давление При установке приборов внешнего контроля (например, таймер, комнатный терморегулятор) убедитесь в том, что они предназначены для термических нагрузок. 14 14 Поверните ручки 4 и 5 в максимальное положение (Рис. 6.5) To…
-
Ensure that the flue terminal is sited correctly
in accordance with the flue fitting instructions. Убедитесь, что система дымохода расположена правильно в соответствии с инструкциями по установке. Чтобы проверить отходящие газы: 1 Снимите заглушки, показанные на рис. 6.8 2 Подключите анализатор к точкам отбора отходящих газов или забора воздуха.…
-
Explain and demonstrate the function of time
and temperature controls (if fitted). Explain how to turn off the appliance for both short and long periods and advise on the precautions necessary to prevent damage should the appliance be inoperative when freezing conditions may occur. Fill in the details required on the Boiler Guarantee…
-
7. Gas conversion
7. 7.1. Warnings 7.1. Предупреждение Procedures to adapt the boiler to the type of gas available must be carried out by a competent and responsible person. More detailed instructions, relating to the procedures for adapting the boiler to the type of gas available and subsequent calibration described…
-
Re-assemble the burner, the front panel of the combustion chamber and the removable front of the air-tight chamber. 6 Установите на место горелку, переднюю панель камеры сгорания и съемную переднюю часть герметичной камеры. 7 Turn on the electricity supply to the boiler, switching on the fused spur…
-
8. Maintenance
8. 8.1. Warnings 8.1. Предупреждения The procedures detailed in this chapter must be carried out only by a professionally qualified person. Thus you are advised to contact an Authorised Service Agent. Действия, описанные в данной главе, должны выполняться только профессиональным и квалифицированным…
-
Side panels
3 Loosen the screws B. Bring the bottom of the panels away from the boiler and lift them, freeing them from the top hooks (Fig. 8.2). Боковые панели 3 Ослабьте винты В. Отодвиньте нижнюю часть панелей от котла и приподнимите их, освободив от векхних крючков (рис 8.2). 8.3. Emptying the d.h.w. system…
-
8.6. Checking the pressurisation in
the expansion vessel 8.6. Проверка предварительного давления в расширительном баке Empty the central heating system as described in section 8.4 of this chapter and check that the pressure in the expansion vessel is not less than 1 bar. See also section 4.6 of this manual. Опорожните систему…