First solar power station starts working in Transcarpathia

537 0
20 August 2012

In Uzhhorod district of the Transcarpathia region, the solar power station has been built and put into service.

The installed capacity of power plant, which construction began in 2011, totals 5.4 MW.

Photovoltaic panels will annually produce about 4.8 million kWh of electricity, it is enough for providing of more than 1.3 thousand households with a monthly consumption of 300 kWh.

On Thursday, the National Energy Regulatory Commission (NERC) decreed to implement electricity produced at the solar station under green tariffs.